With construction so far along, we can see how dramatically the new Charlesview Residences has changed the Brighton Mills site over the last two years.  Most people in the neighborhood can still remember the shopping center with Frugal Fannies and K-Mart ,an old McDonalds, and a tremendously large parking lot.

Apple Maps Charlesview

Apple Maps Image of Charlesview Residences Construction

In fact, if you look at Google Maps you can still see a satellite image of the old shopping center.  Apple Maps has recently released the first mapping service satellite image of the new Charlesview Residences, showing the prepared site, the topped off underground garage, and the beginnings of the mid-rises on Western Ave.

 But, what was there before all of our construction and before the suburban style box store shopping center?

This excerpt from a 1909 map shows what has and hasn’t changed a lot in the last century.  A large cordage (rope) factory operated on what remains the Brighton Mills Shopping Center and a portion of what is now the Charlesview Residences. Most of the Charlesview Residences site, highlighted in blue on the historic map, was laid out for residential development in 1909.  This part of the city at the time was both a rapidly growing “streetcar suburb” and a center of industrial jobs itself.  The small lot, single and 2- and 3-family homes that we love were built quickly along side streets like Antwerp and Litchfield.  You can see many plots on this map that still lack the yellow square that denote the houses.  Just across the railroad tracks (now the MassPike and tracks) were the massive Brighton Stock Yards, which provided meat to the city and beyond.  Today, that site is being redeveloped by New Balance into a major mixed-use center.

Charlesview 1909

Charlesview 1909. Click to enlarge.

Cities and neighborhoods always change and evolve.  We’d like to think that bringing homes back to the neighborhood continues the work of building a Boston neighborhood urban fabric that was underway when this 1909 map was made.

Advertisements

A Bit of Everything on Site

Despite several severe weather events through the winter, work at the Charlesview Residences is moving along quickly.  This March is a fascinating time on site, with a range of construction conditions from finished units all the way down to bare foundations ready to be framed.

Unit 202 in Building D1 was the first to be completed, and the construction, architecture, development, and property management teams tested their punch list process on this unit. Punch listing has now moved through all of the 2nd floor units and will proceed to the 3rd floor next week with a goal of one floor per week until D1 is finished.

IMG_0182_email

The interiors of apartments in Building E1 trail those in D1.  Here is a look at a kitchen on the 5th floor of E1, which will be the last floor to be finished in that building. Counter-tops and appliances need to be installed in the kitchen, and the rest of the unit will get flooring.

IMG_0245

The interiors of C-block townhomes are moving just behind the interiors of E1.  Here is a look inside C1, where countertops, appliances, flooring, and the last interior doors remain to be finished.

IMG_0281

Outside on C-block, siding, hardie trim, roofing, and other exterior work is complete on 3 of the 5 townhomes.

100_2229

Next door on A-block, final exterior work has begun with trim and siding.  Interior work on A-block is also gearing up to begin now.

IMG_0352

With framing complete on A-block and finishing on Building E2, crews have moved over to B-block and will begin on D-block next week.  There are 54 framers on site most days now, but during days like today with snow or freezing temperatures framing work must pause. Below is B5 framed to the roof and B6 moving onto the 3rd floor.

IMG_0345

With framing approaching completion on E2 exterior work there has continued with window and granite installation, as seen below.

IMG_0358

Inside E2, crews are doing the rough-in for mechanical, electrical, and plumbing systems. Drywalling has yet to begin in E2, so wood-framed interiors can still be seen.

100_2137

The framing crews that finished E2 will begin framing D-block townhomes next week as the panelized materials arrive on site.  The foundations for those townhomes can be seen in the foreground below with the mid-rises in the background. This summer, the new Charlesview, Inc. office will be on the foundation seen in the center of the photograph.

IMG_0354

The background of the photo above also shows the exterior work of the E1 mid-rise moving towards completion.  Yellow insulation can be seen on the building’s west face where metal panel installation will follow.

The development is now about 75% construction completion, so this fascinating range of conditions will not last for long as our crews hustle towards the finish.