Building Exterior Progress on Western Ave

Coming down Western Ave, the finished appearance of the Western Ave face of the new Charlesview is taking shape. On D1, masonry and many of the windows are in place. On the larger E1 building, sheathing and waterproofing is on, showing the building’s pattern of windows and bays. The team is focusing on the uses and occupants of the retail and community spaces on the ground floor. Click any image to enlarge.

image

Completed brick portion of the D1 building, with metal panel and glazing to come

image

Looking south from Western down the future Antwerp St

image

Close view of D1 elevations

image

D1 building from down Western Ave

Behind the building facades, the interiors of the two midrise buildings are rapidly progressing. Unit framing, drywall, tubs and mechanical/electrical/plumbing systems are all in progress.