The first concrete deck over the roof of the garage is being poured by concrete sub JL Marshall today.  This particular pour is an important step in the construction sequencing; that section is where the crane will sit to erect the first Western Ave midrise once the concrete cures to the proper strength next month.  The garage floor slab pours will follow each deck-level pour.

image

Workers spread newly poured concrete on the garage deck