Concrete Garage Structure Progressing

Over the holidays, JMA, J. Derenzo Co. (site contractor) and J.L. Marshall (concrete) continued progress on the garage structure.  Excavation is nearing an end as soil removal will finish near the end of the month.  As the excavation bottom has become available, formwork and reinforcing rebar has been placed and concrete foundations have been poured.  Nearly three-quarters of the perimeter footings are complete. 

Above the footings, nearly a third of the garage walls have already been completed.  The garage work continues to benefit from the mild winter weather (until today!) and JMA aims to begin installing the garage deck steel in March.

The photos below captured the garage structural work on site today…