The City of Boston and Charlesview have layers and layers of importance to one another. As the steel buildings rise along Western Avenue, downtown Boston comes into view. And with activity ramping up all over the site, there are now over 120 construction workers on the jobsite each day, priming the Boston economic recovery and great local jobs. We move closer and closer to realizing the vision of preserving Charlesview as a critical housing asset for Allston-Brighton families.
See the gallery below for lots of great images around the site (click any image to enlarge and launch slideshow)
- The first townhouse foundation is formed along Telford Street, near STAR Market
- The shape and massing of Building D1 comes into view, looking from the south
- A closer view of the steel framing of Building D1
- Boston views start to become apparent from the 4th floor of Building D1
- A view of the third floor of Building D1 with steel and concrete in place
- A view of the E1 framing progress, taken from D1, looking across what will be Antwerp Street extension
- Workers prepare the reinforcement for the concrete deck to be poured later this week.
- Progress continues inside the garage on mechanical and plumbing.
- Street wall coming into shape: Steel erection of Building E1 in progress, with the steel framing of Building D1 completed in the background.